Louisiana St Sewer Modifications and CSO-064 Inline Storage (ILS)
WHY IS BUFFALO SEWER DOING THIS PROJECT?
Buffalo Sewer is working to reduce combined sewer overflows (CSOs) impacting surface waters. This project will replace undersized sewer pipes with larger sewer pipes to increase storage volume, which will help to reduce overflows to the Buffalo River.
WILL THIS PROJECT IMPACT THE PLANNED LOUISIANA STREET STREETSCAPE AND BRIDGE REPLACEMENT PROJECT?
Buffalo Sewer has been in communication with the City of Buffalo Department of Public Works regarding project schedules. Construction of this sewer project will be completed before construction starts for the streetscape improvements and bridge replacement.
PROJECT LOCATION & TRAFFIC IMPACTS
What can I expect during construction?
Temporary noise and dust will be minimized as much as possible. Sewer odors will NOT be present in homes, but may be present outside.
Residents and visitors will see:
Partial or full road closures
Sidewalk closures
Limited streetside parking
Traffic detours
Southbound bus stop closed at intersection of Louisiana Street and South Street (potential for relocation)
When will construction begin?
| Construction is anticipated to start in Fall 2027/Spring 2028 and finish by June 2029. Notices will be hand-delivered to residents at least one week before construction starts. | ![]() |
Will my service be affected?
Residents may experience temporary sewer service interruption for a few hours at most. Residents will be notified of construction in advance and details will be provided at that time.
How is this project being funded?
Buffalo Sewer will pay for this project with low interest loans and will seek New York State grant funds to supplement the project funding.
Where can I find more information?
For further information, please call / email Buffalo Sewer.